Project TypeVerizon Data Center
LocationPompano Beach, FL

Description of Project:

Hypower provided a complete electrical scope for a 30,000 sq. ft. expansion of a critical Data Center for the 5G MEC, including a new main service, generators, UPS systems, and PDUs.
The project encompasses FPL installation, power distribution, switchgear, security systems, lighting, lightning protection, grounding, and seismic supports. Hypower also installed owner-furnished 3,000 KW generators, 600 KVA UPS systems, and performed commissioning, testing, and a full switchgear coordination study.

Scope Includes:

  • Provide new primary FPL conduit and directional bore under the existing street.
  • Provide and install conduits for the tele\data system to the existing system in an open and operating building.
  • Provide and install conduits and conductors from the secondary.
  • Installed owner-supplied power distribution equipment, commissioning, and testing.
  • Provide and install all switchgear and branch electrical panels.
  • Switchgear Coordination Study or Short-Circuit Analysis.
  • Security, CCTV, and access control systems.
  • Install the (2) owner-furnished 3,000 KW generator systems and miscellaneous generator support accessories: battery charger, jacket heaters, ATS, control panels, etc.
  • Provide and install 600 kVA UPS systems and all associated components, including battery cabinets.
  • Install the owner-provided PDUs.
  • Provide and install all Exterior and Interior Lighting & Site Lighting Fixture packages and Controls.
  • Lightning Protection System.
  • Provide and install a new cable tray and fiber duct in the server room.
  • Seismic supports for electrical conduits.
  • Exterior and interior grounding.
Year

2024

Client

AECOM TISHMAN

Category

Data Centers, Electrical Construction