hypower-electrical-construction--health--FIU
Project TypeComplete Electrical Construction
LocationMiami, FL

Description of Project
Hypower has installed complete electric services for the Nursing & Health Sciences (NHS) facility which encompasses 115,000 square feet of space housing state-of-the-art interactive skills laboratories, extensive computer suites, specialized training, evaluation, study areas, and lecture hall.  It serves all departments of the CNHS: nursing, physical therapy, occupational therapy, communication sciences & disorders, athletic training, health sciences, and health information management. This fast track project was completed on an 18 month schedule involving 24,000 man hours.

Scope Includes

All Division 16 electrical work

  • Demolition and relocation of existing site electrical
  • Temporary electrical requirements
  • Primary electrical service and power
  • Lighting
  • Fixtures in all areas
  • Reroute existing site lighting circuit
  • Remove existing light pole
  • Complete system of motion control switches
  • Switchgear and feeders
  • Transformer and ductbank
  • Feeders for power distribution equipment
  • Surge suppression
  • Panels
  • Interior lighting and lighting controls
  • HVAC disconnects and power wiring
  • Telephone/Data/Cable TV System including new ductbank
  • Security/CCTV/Card Access Control System
  • Lightning Protection System
  • Fire Alarm and detection system
  • Emergency generator
  • 250 kW diesel, weatherproof enclosure
  • 1500 gallon sub-base fuel tank
FIU College of Nursing & Health Sciences-LEED Silver
Year

2010

Client

Skanska

Category

EDUCATION