Description of Project:

The project consisted of FPL Duct Bank System around the new City Center in Downtown WPB incorporating a Jack and Bore across FEC railway. The scope included placement of MH’s and conduit for several different utilities (FPL, ATT, Peoples Gas) in downtown West Palm Beach. Hypower Inc. organized a utility consortium to minimize construction in the downtown area by doing a joint trench venture.

Role: Subcontractor- Underground Power Services Division

Completed in 2009



 

Latest News
TRANSMISSION & DISTRIBUTION WORLD
Latest News
FEATURED PROJECT
Seaworld T-Line RelocationSeaworld T-Line Relocation
Relocation of existing 115KV Transmission Line. Constructed over the top of existing lines. Spans were in excess of 850ft long. Removed all the existing lines underneath and cut over the distribution to an underground feed.