Dover Air Force Base - Dover, DE

Relocate Overhead Electrical System #3, bury overhead electrical to underground.

Role: Subcontractor Power Services Overhead

Completed in 2010

 

Latest News
TRANSMISSION & DISTRIBUTION WORLD
March 3, 2015 - What the Grid Should Enable
Latest News
FEATURED PROJECT
LCEC 138kV Pole Change OutLCEC 138kV Pole Change Out
Changed out 60 Hot Structures. Coordinated work with Everglades National Park and Panther Reserve to ensure land was preserved. Used Track Equipment to navigate through swamp land. Rebuilding old construction.