Curtis H. Stanton Energy Center Combined Cycle Generating Unit B Foundations - Orlando, FL

Description of Project:

  • Construct infrastructure for 283 megawatt (MW) integrated gasification combined cycle generation unit added to an existing 656 MW combined-cycle generating unit
  • Installed 70,000 ft. of 4” EB-20 PVC Duct in cast foundations
  • Installed plant counterpoise grounding system comprising 230 - 40 ft. Cadwelded 4/0 grounding rods.

Completed in 2008

 

Latest News
TRANSMISSION & DISTRIBUTION WORLD
Latest News
FEATURED PROJECT
LCEC 138kV Pole Change OutLCEC 138kV Pole Change Out
Changed out 60 Hot Structures. Coordinated work with Everglades National Park and Panther Reserve to ensure land was preserved. Used Track Equipment to navigate through swamp land. Rebuilding old construction.