FAU Stadium
Boca Raton, FL
Description of Project:
- Higher Education
- Electrical, Sports Lighting and Fire Alarm for 30,000 Seat Division I Football Stadium
- Biggest challenge was the schedule. Taking a large, complex electrical project from groundbreaking to opening kickoff (October 15, 2011) in less than one year.
- The project was bid with 66% design documents and final engineering as well as a substantial VE package (presented by the team) was all worked out as construction started.
Date of Construction: 2011